Table of Contents...

1.0>Supplemental Overview 3 2.0>Roof Attachment Solutions 3...

2.1>Composition (Asphalt Shingle) Roof Applications 3 2.2>Metal Roof Applications 4 Corrugated Metal 4 Trapezoidal Metal 4 Metal Standing Seam 4 2.3>Tile Roof Applications 4 Standoffs 4 Hanger Bolts 5 Tile Hooks 5 Tile Removal 5 Wood shake roof 5 2.4>Flat Roof Applications 5...

3.0>Installing on Steep Pitched Roofs 5...

3.1>Fall Protection 5 3.2>Staging 6 3.3>First Row Techniques 6...

4.0>Drop-in and Pivot Lock Techniques 6...

4.1>Tolerance Takeup 6 4.2>Top down installation 6 4.3>East-West Drop-in 7 4.4>Helpful Hints 7...

5.0>Wire Management Techniques 7...

5.1>Series Wiring 7 5.2>Home Runs 8 5.3>Wire Management if Module Leads are too Short 8 5.4>Home run routing 8 5.5>Grounding Array During Installation 8...

6.0>Field Installation of Micro-inverters and DC to DC Converters 9...

6.1>Enphase Micro-inverters 9 6.2>SolarEdge 9...

7.0>Staggered Modules 9 8.0>Installing Around Obstructions 10 9.0>Miscellaneous 10...

Version 1.0, Copyright 2010 Zep Solar, Inc....

1.0 > Supplemental Overview...

This guide provides additional techniques and hints for installing Zep System II PV mounting systems not found in the Zep System II Installation Manual. It is not intended to replace the installation manual and should be read after reading the installation manual in its entirety. For questions about this document or any other technical aspect of Zep System II, please call Technical Support at (415) 479-6900, available to answer questions from 9-5 PST....

2.0 > Roof Attachment Solutions...

is the responsibility of the designer/installer to ensure that the str...